In the humid wellness area we used mould-resistant epoxy grout.
Sample project. Real photos and description coming soon.

- Project
- Hotel chain, High Tatras
- Type
- Commercial
- Space
- Wellness
- Location
- Vysoké Tatry
- Year
- 2025
The challenge
The lobby and 24 bathrooms were renovated while the hotel stayed open. We had each floor for only five days.
Material had to reach the upper floors without a goods lift.
What we did
We surveyed all bathrooms in one go and had the slabs cut to size in advance, so each floor was installation only.
Slabs went up the stairs on special carrying frames with no risk of cracking.
In the lobby the wall behind reception is a single 160 × 320 cm slab, with cut-outs for lighting and cameras.
Tiles used
- Format
- 160 × 320 cm
- Material
- Porcelain slab, Calacatta
- Surface
- Matte
- Thickness
- 6 mm
- Joints
- 2 mm, epoxy
- Area
- 120 m²
- Duration
- 7 weeks, floor by floor
Scope of work
- 01Survey of 24 bathrooms and the lobby
- 02Cutting slabs to size in advance
- 03Carrying slabs up the stairs on frames
- 04Installation while the hotel was open
- 05Cut-outs for lighting and equipment
„They hit every deadline and guests barely noticed the renovation.“